Passenger Line workday recap for Saturday, June 19, 2021
What a great turn out we had today including the rain. The morning started earlier than normal as the crew started arriving before 8 a.m. and went right to work to connect the last fifty feet of track at the man crossing. Scott and David E. spent time on address future drainage needs closer to the station area by digging a trench for a drainage pipe.
What a great turn out we had today including the rain. The morning started earlier than normal as the crew started arriving before 8 a.m. and went right to work to connect the last fifty feet of track at the man crossing. Scott and David E. spent time on address future drainage needs closer to the station area by digging a trench for a drainage pipe. Just as the last bit of ballast was spread it began to sprinkle. The crew cleaned up and had lunch and decided to stop for the day. This leaves us just fifty feet short of connecting the east loop to the gate crossing which leaves us about 200-feet to complete the passenger line. The crew today consisted of Wes, Gene, “Bob2”, Norm, Rick, Peter, Robby, David E., Scott and special guest Chris P. and his family. The crew also decided how the decking for the man crossing will look and plan to get that portion installed in the coming weeks as well.
While our next official workday is not until Saturday, July 10th we are talking about a mini workday at the site to finish connecting the east loop to the grade crossing before then. Be on the lookout for a mini-workday announcement in the next week or so.
Workday scheduled for Saturday, June 19th at 8:30 a.m.
As you have seen from many of the most recent posts progress on the passenger line is progressing. We are just one workday away from connecting the east loop with the passenger line all the way to the man gate (restroom building area) leaving use just about 250-feet of track to complete the passenger line project.
Let us make Saturday, June 19th another productive workday. Make sure you bring tools, water, lunch, sunscreen, and a good sense of humor.
As you have seen from many of the most recent posts progress on the passenger line is progressing. We are just one workday away from connecting the east loop with the passenger line all the way to the man gate (restroom building area) leaving use just about 250-feet of track to complete the passenger line project.
Let us make Saturday, June 19th another productive workday. Make sure you bring tools, water, lunch, sunscreen, and a good sense of humor.
Impromptu Workday recap for Saturday, June 12th - Transition from "Big Dig" to passenger line
What a difference just a couple of weeks make. We now have a new 60-foot gate grade crossing at the main entrance to the property which is part of the new passenger line. The crew, which consisted of Wes, Norm, Gene, “Bob"2”, Scott, Robby, and Calvin, spent the day working on finishing the grade crossing grading and packed in about 120-feet of crusher run in the forms between the gate crossing and the man crossing. The crew also installed about 70-feet of track between the crossings.
What a difference just a couple of weeks make. We now have a new 60-foot gate grade crossing at the main entrance to the property which is part of the new passenger line. The crew, which consisted of Wes, Norm, Gene, “Bob"2”, Scott, Robby, and Calvin, spent the day working on finishing the grade crossing grading and packed in about 120-feet of crusher run in the forms between the gate crossing and the man crossing. The crew also installed about 70-feet of track between the crossings.
During all the work we did have a small incident between “Bob2”, a shovel, and a rake. While the rake only had minor bruises the shovel on the other hand did not fare as well. Medical attention was requested but not sure what the final diagnosis will be for the shovel.
Meanwhile, Wes went crazy and tackled grass cutting, weed eating the fence, and more. Calvin also marked the first official car across the gate crossing. Our next official workday will be this Saturday, June 19th at 8:30 a.m. The focus of the day will be to finish laying track to the man crossing and connect the east loop to the gate crossing. Should be a great day with some real progress. We look forward to seeing everyone. Make sure you bring plenty of water, sunscreen, lunch, and a good sense of humor.
What a difference a year makes. Look at what we did in June of 2020
In June of 2020, the club was working full steam ahead on extending our grey container another 20 feet. The project consisted of finishing the ash pit line and adding two tracks to the back of the container. The project consisted of finishing the ash pit line, building a retaining wall, adding a 20-foot container, and lots of track work. Check out some pictures from our project from June 2020.
As we look forward to June 2021 the “Big Dig” passenger line project is well underway. The plan is to get it all in by the end of summer weather and time permitting. Our next official big workday is scheduled for Saturday, June 19th at 8:30 a.m.
In June of 2020, the club was working full steam ahead on extending our grey container another 20 feet. The project consisted of finishing the ash pit line and adding two tracks to the back of the container. The project consisted of finishing the ash pit line, building a retaining wall, adding a 20-foot container, and lots of track work. Check out some pictures from our project from June 2020.
As we look forward to June 2021 the “Big Dig” passenger line project is well underway. The plan is to get it all in by the end of summer weather and time permitting. Our next official big workday is scheduled for Saturday, June 19th at 8:30 a.m.
Coming up on the calendar
Are you looking for something to do this summer? We are looking for volunteers to help us finish a few things.
North Georgia Live Steamers is looking for some volunteers this summer. As we work on reopening this fall as the area and the world move forward from the pandemic, we have been busy on a few projects. We are in the home stretch of a major railroad project and could use some extra hands, machinery, and encouragement to complete this project by the end of the summer.
Over the past two years we have been working on expanding the railroad so we can handle more traffic, riders, and just make the overall experience that much better. Over many Saturdays this summer a crew will be at the site working on the last 300-feet of track and could use some extra hands.
North Georgia Live Steamers is looking for some volunteers this summer. As we work on reopening this fall as the area and the world move forward from the pandemic, we have been busy on a few projects. We are in the home stretch of a major railroad project and could use some extra hands, machinery, and encouragement to complete this project by the end of the summer.
Over the past two years we have been working on expanding the railroad so we can handle more traffic, riders, and just make the overall experience that much better. Over many Saturdays this summer a crew will be at the site working on the last 300-feet of track and could use some extra hands.
If you are interested in volunteering or learning more about the project, please reach out to Robby our Club Secretary for more details on how you can get involved. No experience necessary just a willingness to get involved. If you are unable to volunteer and would like to make a donation to help us complete the project your consideration would be appreciated.
Things to bring on a workday:
Plenty of water
A lunch
Cordless drills
Good sense of humor
Sun Screen
"Big Dig" Workday Recap For Saturday, May 29, 2021
The “Big Dig” continued on the passenger line project as a small group went to the site to pull the form boards on the grade crossing and set forms for track laying to begin between the new main gate crossing and the man crossing. I’m being told that Scott performed miracles with the wire wheel and grinder to clean the concrete off the rails. Be on the look out for a workday to lay track in the coming days and weeks.
The “Big Dig” continued on the passenger line project as a small group went to the site to pull the form boards on the grade crossing and set forms for track laying to begin between the new main gate crossing and the man crossing. I’m being told that Scott performed miracles with the wire wheel and grinder to clean the concrete off the rails.
Be on the look out for a workday to lay track in the coming days and weeks.
The "Big Pour" workday recap for Monday, May 24, 2021
Wow what a hot day but we did get the new grade crossing poured. The crew consisted of Wes, Gene, Norm, Scott, Robby, Ben, “Bob”, and Joe. In typically fashion for us the concrete truck was delayed several hours which pushed us into the hottest part of the day. Progress was slow but the team pushed through it. As you might imagine the concrete will not be ready to drive on for a week or so. We had a little extra concrete which gave Joe and Norm the opportunity to use it near the west end of the yard that has a drain that keeps clogging with dirt. Now the concreate should help reduce the clogging.
Wow what a hot day but we did get the new grade crossing poured. The crew consisted of Wes, Gene, Norm, Scott, Robby, Ben, “Bob”, and Joe. In typically fashion for us the concrete truck was delayed several hours which pushed us into the hottest part of the day. Progress was slow but the team pushed through it. As you might imagine the concrete will not be ready to drive on for a week or so. We had a little extra concrete which gave Joe and Norm the opportunity to use it near the west end of the yard that has a drain that keeps clogging with dirt. Now the concreate should help reduce the clogging.
Below is what we have officially on the calendar next but as always subject to change. Speaking of up next on the calendar our next club meeting will be on Saturday, June 5th. As has become customary over the past couple of years this is also a club fun day. We could use some extra hands between now and then to do a once over on the railroad and the grass also needs to be cut.
Upcoming Events
"Big Dig" workday recap for Saturday, May 22nd
Another big day working on the passenger line project. The day consisted of grading nearly 200’, setting the man crossing, and adding more conduit under the new 60’ gate crossing. The crew, which consisted of Gene, “Bob2”, Norm, Calvin, Elijah, David E., Wes, Robby, Tyler, James, and Jaxon also spent time saying goodbye to James and Jaxon as the family moves out of the area onto a new adventure. We wish them the best and hope to see the family around a railroad in the future. The crew also visited with James and Jaxon as they prepare to move out of the area onto a new adventure and hope to see them around the hobby one day in the near future.
Check out these pictures from the day’s activities. Don’t forget if you are available on Monday, May 24th the 60’ gate crossing will get nearly 7 yards of concrete and could use all of the extra hands as possible. The plan is to arrive around 8:30 a.m. with the concrete truck arriving in the 9 o’clock hour. If all goes well, we should be done around lunch time.
Another big day working on the passenger line project. The day consisted of grading nearly 200’, setting the man crossing, and adding more conduit under the new 60’ gate crossing. The crew, which consisted of Gene, “Bob2”, Norm, Calvin, Elijah, David E., Wes, Robby, Tyler, James, and Jaxon also spent time saying goodbye to James and Jaxon as the family moves out of the area onto a new adventure. We wish them the best and hope to see the family around a railroad in the future. The crew also visited with James and Jaxon as they prepare to move out of the area onto a new adventure and hope to see them around the hobby one day in the near future.
Check out these pictures from the day’s activities. Don’t forget if you are available on Monday, May 24th the 60’ gate crossing will get nearly 7 yards of concrete and could use all of the extra hands as possible. The plan is to arrive around 8:30 a.m. with the concrete truck arriving in the 9 o’clock hour. If all goes well, we should be done around lunch time.
The "Big Dig" continues this Saturday, May 22nd @ 8:30 a.m.
The “Big Dig” continues this Saturday, May 22nd as we continue to dig and set the passenger line in place. We will have “Bob2” onsite helping with grading the passenger line west of the new grade crossing. The plan for the day is to set the man crossing by the restroom area and start setting forms heading towards the new grade crossing. We will also be doing a final check on the grade crossing making sure everything is ready for the concrete to be poured on Monday, May 24th.
The “Big Dig” continues this Saturday, May 22nd as we continue to dig and set the passenger line in place. We will have “Bob2” onsite helping with grading the passenger line west of the new grade crossing. The plan for the day is to set the man crossing by the restroom area and start setting forms heading towards the new grade crossing. We will also be doing a final check on the grade crossing making sure everything is ready for the concrete to be poured on Monday, May 24th.
The plan for next weekend, Saturday, May 22nd, is to continue to dig out the area west of the grade crossing, start laying track, set the man crossing, and finish up any last minute details for the concrete pour on Monday, May 24th. A busy weekend planned for sure and looking forward to seeing everyone. Make sure you bring tools, lunch, sunscreen, plenty of water, and a good sense of humor.
The "Big Dig" continues with the latest workday recap from May 15, 2021
We had a small crew on hand today to take care of a few preparation items for next weekend’s work and concrete pour on Monday, May 24th. The crew, which consisted of Elijah, Norm, Scott, Ben, and “Bob”, took a divide an concur approach to the day working on the unofficial driveway entrance from the street, spread and leveled gravel for the next member container, and dug out 160’ west of the new grade crossing towards to man crossing.
We had a small crew on hand today to take care of a few preparation items for next weekend’s work and concrete pour on Monday, May 24th. The crew, which consisted of Elijah, Norm, Scott, Ben, and “Bob”, took a divide an concur approach to the day working on the unofficial driveway entrance from the street, spread and leveled gravel for the next member container, and dug out 160’ west of the new grade crossing towards to man crossing.
The plan for next weekend, Saturday, May 22nd, is to continue to dig out the area west of the grade crossing, start laying track, set the man crossing, and finish up any last minute details for the concrete pour on Monday, May 24th. A busy weekend planned for sure and looking forward to seeing everyone. Make sure you bring tools, lunch, sunscreen, plenty of water, and a good sense of humor.
The "Big Dig" has begun- Impromptu workday recap from Saturday, May 8th
One thing that is constant is change when you are planning things. This past weekend we had planned on working on getting the next member container area ready, which we did, however delivery of the container was delayed because of the quality of the container available was not as good as we had hoped. While continue to search for the next container we pivoted on Friday and put together a crew for Saturday impromptu workday and started the “Big Dig” portion of the passenger line project. The crew consisted of Ben, “Bob”, Gene, “Bob2”, Norm, Robby, Wes, and John. Scott was also at the site working on installing some additional electrical in the grey container. About 90% of everything was completed but we are looking for any individuals who are available this week to install the rebar so we can schedule a concrete truck to pour on Saturday, May 15th. Contact Norm if you have time this week as he will be coordinating the installation of the rebar.
One thing that is constant is change when you are planning things. This past weekend we had planned on working on getting the next member container area ready, which we did, however delivery of the container was delayed because of the quality of the container available was not as good as we had hoped. While continue to search for the next container we pivoted on Friday and put together a crew for Saturday impromptu workday and started the “Big Dig” portion of the passenger line project. The crew consisted of Ben, “Bob”, Gene, “Bob2”, Norm, Robby, Wes, and John. Scott was also at the site working on installing some additional electrical in the grey container. About 90% of everything was completed but we are looking for any individuals who are available this week to install the rebar so we can schedule a concrete truck to pour on Saturday, May 15th. A little late on my part but Norm will be heading out with a few people on Tuesday, May 11th at 8;30 a.m. to work on the rebar. If you are able to help I’m sure they’d take what ever you can offer.
Assuming everything goes well, and the weather cooperates we will need extra help on Saturday, May 15th as about 8 or 9 yards of concrete is delivered and poured. If for some reason we are not able to pour on Saturday, we will begin grading work from west side of the new crossing towards the station area in preparation of track to be installed in a future workday. If you are available on Saturday, May 24th please arrive around 8:30 a.m. ahead of the concrete truck to help finalize any last-minute details before the pour which will happen around 10 a.m.(‘ish).
As was mentioned earlier Scott worked in the grey container installing more conduit so the lights can be turned on and off from either end of the container.
Electrical work by Scott M.
What’s on the calendar
All dates are subject to change
Train Rides on Saturday, May 15th Cancelled
North Georgia Live Steamers has made an adjustment to the 2021 train ride schedule. The May 15th public run day has been Cancelled. While things continue to improve in our community with COVID-19 the safety of our members and public remain our top priority. We continue to monitor things and look forward to hitting the rails again very soon. As of Tuesday, May 4th here is a list of our remaining schedule for the 2021 season. The current operating schedule is Saturday, October 2nd, and November 20th from 1 p.m. to 4:30 p.m.
North Georgia Live Steamers has made an adjustment to the 2021 train ride schedule. The May 15th public run day has been Cancelled. While things continue to improve in our community with COVID-19 the safety of our members and public remain our top priority. We continue to monitor things and look forward to hitting the rails again very soon. As of Tuesday, May 4th here is a list of our remaining schedule for the 2021 season. The current operating schedule is Saturday, October 2nd, and November 20th from 1 p.m. to 4:30 p.m. These dates are subject to change. Riders must be at least 18 months old or older. No expectant mothers allowed to ride on the railroad. Tickets can be purchased on site. CASH Only. No Credit Cards accepted at this time.
While we wait to reopen the members and other volunteers of North Georgia Live Steamers continue to work on expanding the railroad. If you or someone you know would like to donate to North Georgia Live Steamers to help us with our projects, please visit our donations page for more information.
We look forward to seeing you around the railroad soon.
"Big Dig" Workday Cancelled for Saturday, April 24th – Rain, Rain Go Away
The “Big Dig” workday scheduled for Saturday, April 24th has been CANCELLED because of this stuff called rain. Be on the lookout for a reschedule date in the next couple of weeks.
The “Big Dig” workday scheduled for Saturday, April 24th has been CANCELLED because of this stuff called rain. Be on the lookout for a reschedule date in the next couple of weeks. A tentative reschedule date has been set for Saturday, May 22nd with concrete being poured on Monday, May 24th. Weather permitting.
What’s next on the calendar?
Train Ride Scheduled for Saturday, May 15th is Cancelled
North Georgia Live Steamers has made an adjustment to the 2021 train ride schedule. The May 15th public run day has been Cancelled. While things continue to improve in our community with COVID-19 the safety of our members and public remain our top priority. We continue to monitor things and look forward to hitting the rails again very soon. As of Tuesday, May 4th here is a list of our remaining schedule for the 2021 season. The current operating schedule is Saturday, October 2nd, and November 20th from 1 p.m. to 4:30 p.m. These dates are subject to change. Riders must be at least 18 months old or older. No expectant mothers allowed to ride on the railroad. Tickets can be purchased on site. CASH Only. No Credit Cards accepted at this time.
North Georgia Live Steamers has made an adjustment to the 2021 train ride schedule. The May 15th public run day has been Cancelled. While things continue to improve in our community with COVID-19 the safety of our members and public remain our top priority. We continue to monitor things and look forward to hitting the rails again very soon. As of Tuesday, May 4th here is a list of our remaining schedule for the 2021 season. The current operating schedule is Saturday, October 2nd, and November 20th from 1 p.m. to 4:30 p.m. These dates are subject to change. Riders must be at least 18 months old or older. No expectant mothers allowed to ride on the railroad. Tickets can be purchased on site. CASH Only. No Credit Cards accepted at this time.
Railroad Location
1632 Centennial Olympic Parkway
Conyers, GA 30013
Reminder: Major Workday planned for Saturday, April 24th at 8:30 a.m.
As a reminder a major workday is planned for Saturday, April 24th. The plan for the day is to bring in heavy machinery and dig the new 60-foot grade crossing and prep the area heading towards the station for the the remaining passenger line track. We could use all the help we can get so we can prep the area for the concrete truck to pour on Monday, April 26th.
As a reminder this workday is in place of our public run day which has been cancelled. Make sure you bring power tools, lunch, drinks, and a good sense of humor. If you have any questions please contact Norm or Robby.
As a reminder a major workday is planned for Saturday, April 24th. The plan for the day is to bring in heavy machinery and dig the new 60-foot grade crossing and prep the area heading towards the station for the the remaining passenger line track. We could use all the help we can get so we can prep the area for the concrete truck to pour on Monday, April 26th.
This workday is in place of our public run day which has been cancelled. Make sure you bring power tools, lunch, drinks, and a good sense of humor. If you have any questions please contact Norm or Robby.
Workday Recap for Saturday, April 17th - The prelude to the big dig
On Saturday, a crew went out to the site to take care of some preparation work for next weekends “big dig” and finish preparation for the next member container to be delivered. With the help from Ben and “Bob” much dirt was moved and dug. The rest of the crew consisted of Wes, Gene, Robby, Norm, and David E. who at times seemed to be supervising and contemplating life. Not really a great deal was done by all including determining elevation, confirming placement of grade crossing, location of future man crossing and a whole lot more. The crew surprised themselves on the amount of progress that was made on throughout the day including digging about 30 of the 60 feet needed for the grade crossing.
On Saturday, a crew went out to the site to take care of some preparation work for next weekends “big dig” and finish preparation for the next member container to be delivered. With the help from Ben and “Bob” much dirt was moved and dug. The rest of the crew consisted of Wes, Gene, Robby, Norm, and David E. who at times seemed to be supervising and contemplating life. Not really a great deal was done by all including determining elevation, confirming placement of grade crossing, location of future man crossing and a whole lot more. The crew surprised themselves on the amount of progress that was made on throughout the day including digging about 30 of the 60 feet needed for the grade crossing.
During this upcoming week gravel will be delivered for the next member container then on Saturday, April 24th the “big dig” moves into full swing. The day consists of “Bob” and some cousin’s to be onsite helping dig and move dirt. We will need a lot of help throughout the day which includes leveling the gravel for the next member container and of course the grade crossing elements. Make sure you bring shovels, power tools, a hat, lunch, and a good sense of humor. Work will begin around 8:30 a.m.
Member container site grading is now complete. Gravel will be delivered during the week of April 19th and will be ready to level the gravel in preparation for a container to be delivered. A big thanks to Ben and “Bob” for the dirt work.
Impromptu Workday Scheduled for Saturday, April 17th at 8:30 a.m.
A workday has been scheduled for this Saturday. The plan is to prepare an area for a new container and prepare for the "big dig" event for the new grade crossing. Bring lunch, water, and a good sense of humor. Be aware an event is happening at the horse park which may make it a little difficult to enter the site.
A workday has been scheduled for this Saturday. The plan is to prepare an area for a new container and prepare for the "big dig" event for the new grade crossing. Bring lunch, water, and a good sense of humor. Be aware an event is happening at the horse park which may make it a little difficult to enter the site.
Major Workday planned for Saturday, April 24th at 8:30 a.m.
A major workday is planned for Saturday, April 24th. The plan for the day is to bring in heavy machinery and dig the new 60-foot grade crossing and prep the area heading towards the station for the the remaining passenger line track. We could use all the help we can get so we can prep the area for the concrete truck to pour on Monday, April 26th.
As a reminder this workday is in place of our public run day which has been cancelled. Make sure you bring power tools, lunch, drinks, and a good sense of humor. If you have any questions please contact Norm or Robby.
A major workday is planned for Saturday, April 24th. The plan for the day is to bring in heavy machinery and dig the new 60-foot grade crossing and prep the area heading towards the station for the the remaining passenger line track. We could use all the help we can get so we can prep the area for the concrete truck to pour on Monday, April 26th.
As a reminder this workday is in place of our public run day which has been cancelled. Make sure you bring power tools, lunch, drinks, and a good sense of humor. If you have any questions please contact Norm or Robby.
North Georgia Live Steamers 2021 Train Ride Schedule Update
North Georgia Live Steamers has made an adjustment to the 2021 train ride schedule. The April 24th public run day has been Cancelled. While things continue to improve in our community with COVID-19 the safety of our members and public remain our top priority. We continue to monitor things and look forward to hitting the rails again very soon. As of Tuesday, April 6th here is a list of our remaining schedule for the 2021 season.
The current operating schedule is Saturday, May 15th, October 2nd, and November 20th from 1 p.m. to 4:30 p.m. These dates are subject to change. Riders must be at least 18 months old or older. No expectant mothers allowed to ride on the railroad. Tickets can be purchased on site. CASH Only. No Credit Cards accepted at this time.
North Georgia Live Steamers has made an adjustment to the 2021 train ride schedule. The April 24th public run day has been Cancelled. While things continue to improve in our community with COVID-19 the safety of our members and public remain our top priority. We continue to monitor things and look forward to hitting the rails again very soon. As of Tuesday, April 6th here is a list of our remaining schedule for the 2021 season.
The current operating schedule is Saturday, May 15th, October 2nd, and November 20th from 1 p.m. to 4:30 p.m. These dates are subject to change. Riders must be at least 18 months old or older. No expectant mothers allowed to ride on the railroad. Tickets can be purchased on site. CASH Only. No Credit Cards accepted at this time.
Workday Recap for Saturday, March 27, 2021
Our last workday of the month is in the books. The work crew built more track panels, cut more than 500 ties, repaired the railroad, dreamed a lot, and had fun. The crew consisted of Scott, Calvin, Robby, Norm, Elijah, Tyler, Dave E., John, a lizard, and a snake. Joe also stopped by to check on the new riding car frames and from what many of us could tell he loaded his van with some additional supplies to make additional progress on the cars.
The railroad is about 99% operational for our club fun day next Saturday, April 3rd. We need some help with getting the grass cut and getting the club lawnmower running. If you are available to go out and cut grass or work on the club lawnmower let us know. Please note that the motorized switches are still in need of repair and Robby hopes to have them running by Saturday.
As a reminder Saturday, April 3rd is also our next club meeting which is scheduled for 1 p.m. We are expecting a visitor or two from within the hobby along with family and friends. Let us make sure we welcome them. As a reminder this is not a public run day.
Our last workday of the month is in the books. The work crew built more track panels, cut more than 500 ties, repaired the railroad, dreamed a lot, and had fun. The crew consisted of Scott, Calvin, Robby, Norm, Elijah, Tyler, Dave E., John, a lizard, and a snake. Joe also stopped by to check on the new riding car frames and from what many of us could tell he loaded his van with some additional supplies to make additional progress on the cars.
The railroad is about 99% operational for our club fun day next Saturday, April 3rd. We need some help with getting the grass cut and getting the club lawnmower running. If you are available to go out and cut grass or work on the club lawnmower let us know. Please note that the motorized switches are still in need of repair and Robby hopes to have them running by Saturday.
As a reminder Saturday, April 3rd is also our next club meeting which is scheduled for 1 p.m. We are expecting a visitor or two from within the hobby along with family and friends. Let us make sure we welcome them. As a reminder this is not a public run day.
Speaking of our public run day plans. We hope to have an update for everyone at the club meeting.