Project 2: West Loop track repair near the Nicol bridge
The purpose of this project is to repair an area on the west loop near the Nicol bridge that needs about 40 feet of track repaired including moving a switch to a new location in order to provide better transition coming out of a curve heading towards the Nicol bridge. Because of the nature of this repair, it must be completed before our April 13th run day.
Proposed work schedule
Workday #1 (at any time before January 27th) - Identify and build track panel(s) need to be built as well as cut replacement ties that will be installed in numerous places in the area being repaired.
Workday #2 (Saturday, February 24th)- repairing and reworking west loop track section near Nicol bridge.
Workday #3 (Saturday, March 23rd) - All repair work must be completed by this date to make sure the railroad is operational again before our first public run day which is Saturday, April 13th.