One year in on the passenger line project and look at what has been accomplished
Back in July 2020 construction began on the passenger line with the installation of a switch leaving the yard on the west end of the railroad. Soon after a switch in the inner east loop and our first diamond was also installed. Fast forward to July 2021 with more than 30 weekends worked we have installed more than 1,400’ of rail, 1,590 railroad ties (give or take), 5,320 screws (give or take), more than 70 track panels, 6 switches, 60’ concrete grade crossing, 30’ pedestrian crossing, a diamond, and countless loads of gravel. This leaves us just 17 more panels to complete this project and the expansion of our mainline will be complete. A big thank you to all of you who have been able to come out and work throughout the year and a big thank you to those that could not come out but cheered us on we thank you.
As we near the completion of this project we also are closing in on our first public run day in nearly two years. We look forward to seeing many of you around the railroad over the next two months as we prepare to re-open the railroad and share our love for trains, the hobby, and more.
I hope you enjoy looking back over the past year at some of the pictures taken just to show how much has been done and how far we’ve come.