Big push to complete the passenger line project
It is amazing how much we have completed over the past year on the passenger line project. On July 25, 2020, we started the project with the installation of the bypass switch.
By the end of August work was in full swing on the east side of the railroad with work on the bypass from the outer loop and installation of a switch and panels from the inner loop heading towards the railroads first diamond.
As we move into September of 2020, we picked up momentum with the installation of the diamond work progressed fast as we moved our efforts beyond the diamond and started laying track that would represent the passenger line. Once it was all said and done, we had laid nearly 200 feet of track and well on our way to the grade crossing that would later be installed in 2021.
So, if you made it to the end of this timeline you might be asking what is next. As of July 2nd, we are 90 days away from the planned re-opening of the railroad with our first public run day since 2019. We are also about 250 feet away from completing the track work to complete the passenger line. We have five official workdays planned between now and October 2nd creating a tight schedule to complete everything. As you plan your next few months please consider coming out and helping us push forward to complete this project. Every set of hands will get us closer to completing this project ahead of our October reopening.
If you have any questions or would like to organize a weekday or weekend workday outside of what is already scheduled please contact Norm or Robby. For those that are reading this and are not part of our club and are interested in volunteering and learning more about our organization please feel free to come out during one of our workdays. If you have any questions about volunteering, please contact Robby for more details.
Hope to see you around the railroad soon.